Straits Arena Upgrades
St. Alban's, Newfoundland and Labrador
Federal contribution
$7,442
Federal share40%
of $18.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Straits Arena Association
- Construction start
- Nov 12, 2019(actual)
- Construction end
- Nov 15, 2019(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Dec 15, 2019
- Construction end6 months earlyforecast May 30, 2020
Also in St. Alban's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53838 in the federal list. How to read these figures.