Bay D'Espoir Rec Plex Coolant System Replacement

St. Alban's, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$126,075
Federal share33%

of $378.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2021
20212022
Built

Approved 12 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of St. Alban’s
Construction start
Jun 15, 2021(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2021
  • Construction end3 months lateforecast Mar 31, 2022

Also in St. Alban's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57016 in the federal list. How to read these figures.