Wet Well Pump House Improvements
St. Alban's, Newfoundland and Labrador
Federal contribution
$119,984
Federal share37%
of $325.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2021
2021
Built
Approved 15 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Albans
- Construction start
- Mar 15, 2021(actual)
- Construction end
- Jul 15, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Dec 1, 2020
- Construction end5 months lateforecast Feb 28, 2021
Also in St. Alban's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56432 in the federal list. How to read these figures.