Back to projects

Marine Drive Sanitary Sewer Improvements - St. Alban's

St. Alban's, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$159,900
Federal share39%

of $408.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Alban’s
Construction start
Jun 15, 2021(actual)
Construction end
Oct 20, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2021
  • Construction end6 weeks earlyforecast Dec 1, 2021