Waterline Replacement St. Brides
St. Bride's, Newfoundland and Labrador
Federal contribution
$236,446
Federal share24%
of $974.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Bride's
- Construction start
- Apr 26, 2021(actual)
- Construction end
- Aug 13, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2021
- Construction end4 weeks lateforecast Jul 15, 2021
Also in St. Bride's