Back to projects

Waterline Replacement – St. Bride’s

St. Bride's, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$236,446
Federal share24%

of $974.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Bride's
Construction start
Apr 26, 2021(actual)
Construction end
Aug 13, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 1, 2021
  • Construction end4 weeks lateforecast Jul 15, 2021

Also in St. Bride's