Southside Dam Upgrade and Chlorination System
St. Bride's, Newfoundland and Labrador
Federal contribution
$214,141
Federal share40%
of $535.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
today
202420252026
BuiltForecast
Approved 17 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Bride's
- Construction start
- Apr 1, 2026(forecast)
- Construction end
- Oct 31, 2026(forecast)