Back to projects

Improvement of Southside Water Reservoir

St. Bride's, Newfoundland and Labrador

approvedDrinking WaterGIS
Federal contribution
$269,953
Federal share40%

of $674.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2023
today
2023202420252026
BuiltForecast

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Bride's
Construction start
Jul 15, 2026(forecast)
Construction end
Sep 15, 2026(forecast)

Also in St. Bride's