Multi-Purpose Centre

Port Hope Simpson, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$663,901
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Port Hope Simpson
Construction start
Sep 9, 2020(actual)
Construction end
Sep 30, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 30, 2020
  • Construction end5 months earlyforecast Feb 28, 2023

Also in Port Hope Simpson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53940 in the federal list. How to read these figures.