Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Port Hope Simpson
- Construction start
- Sep 9, 2020(actual)
- Construction end
- Sep 30, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 30, 2020
- Construction end5 months earlyforecast Feb 28, 2023
Also in Port Hope Simpson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53940 in the federal list. How to read these figures.