Country Road Water and Sewer Upgrades
Port Hope Simpson, Newfoundland and Labrador
Federal contribution
$389,401
Federal share40%
of $973.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
2022202320242025
Built
Approved 3 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Port Hope Simpson
- Construction start
- Sep 2, 2023(actual)
- Construction end
- Nov 30, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2023
- Construction end12 months lateforecast Dec 15, 2023
Also in Port Hope Simpson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62157 in the federal list. How to read these figures.