Country Road Water and Sewer Upgrades

Port Hope Simpson, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$389,401
Federal share40%

of $973.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
2022202320242025
Built

Approved 3 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Port Hope Simpson
Construction start
Sep 2, 2023(actual)
Construction end
Nov 30, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2023
  • Construction end12 months lateforecast Dec 15, 2023

Also in Port Hope Simpson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62157 in the federal list. How to read these figures.