Notley's Drive water and waste water system
Port Hope Simpson, Newfoundland and Labrador
Federal contribution
$435,179
Federal share50%
of $870.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Port Hope Simpson
- Construction start
- Jun 19, 2017(actual)
- Construction end
- Oct 18, 2017(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2017
- Construction end2 weeks lateforecast Oct 1, 2017
Also in Port Hope Simpson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46987 in the federal list. How to read these figures.