Back to projects

Notley's Drive water and waste water system

Port Hope Simpson, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$435,179
Federal share50%

of $870.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Port Hope Simpson
Construction start
Jun 19, 2017(actual)
Construction end
Oct 18, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2017
  • Construction end2 weeks lateforecast Oct 1, 2017

Also in Port Hope Simpson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46987 in the federal list. How to read these figures.