Sewage Lift Station Retrofit - Town of Norris Arm
Norris Arm, Newfoundland and Labrador
Federal contribution
$90,683
Federal share40%
of $226.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Norris Arm
- Construction start
- Sep 30, 2020(actual)
- Construction end
- Jan 30, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2020
- Construction end8 months earlyforecast Sep 30, 2021