Sewage Lift Station Retrofit - Norris Arm

Norris Arm, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$124,543
Federal share34%

of $362.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Norris Arm
Construction start
May 1, 2023(actual)
Construction end
Jun 6, 2023(actual)

Against the original forecast

  • Construction end4 months earlyforecast Sep 30, 2023

Also in Norris Arm

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61116 in the federal list. How to read these figures.