Back to projects

Water and Sewer Replacement

Norris Arm, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$107,592
Federal share40%

of $269.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20242025
Built

Approved 23 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Norris Arm
Construction start
Sep 9, 2024(actual)
Construction end
Oct 9, 2024(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 1, 2024