Street Improvements - Cross Road
Bay Roberts, Newfoundland and Labrador
Federal contribution
$368,249
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Bay Roberts
- Construction start
- Apr 7, 2021(actual)
- Construction end
- Oct 12, 2021(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 1, 2021
- Construction end7 weeks lateforecast Aug 23, 2021
Also in Bay Roberts
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53954 in the federal list. How to read these figures.