Water System Upgrades - Torbay
Torbay, Newfoundland and Labrador
Federal contribution
$217,674
Federal share40%
of $544.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
2020202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Torbay
- Construction start
- Jul 11, 2022(actual)
- Construction end
- Sep 11, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 15, 2022
- Construction end5 months earlyforecast Feb 15, 2024
Also in Torbay