New sidewalks on Torbay Road from Mahon's Road to Juniper Ridge

Torbay, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$695,379
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2021
20212022202320242025
Built

Approved 13 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Torbay
Construction start
Aug 20, 2021(actual)
Construction end
Nov 17, 2024(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 15, 2021
  • Construction end7 weeks lateforecast Sep 30, 2024

Also in Torbay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56765 in the federal list. How to read these figures.