Whiteway's Pond Trail Extension
Torbay, Newfoundland and Labrador
Federal contribution
$8,452
Federal share60%
of $14.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
20232024
Built
Approved 20 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Torbay
- Construction start
- Dec 3, 2022(actual)
- Construction end
- Dec 21, 2022(actual)
Against the original forecast
- Construction start6 months lateforecast May 31, 2022
- Construction end6 months lateforecast Jun 16, 2022
Also in Torbay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63550 in the federal list. How to read these figures.