Secondary Wastewater Treatment and System Upgrades

Tofino, British Columbia

completeWastewaterGIS
Federal contribution
$22.0M
$21,963,600
Federal share40%

of $54.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 27, 2019
202020212022202320242025
Built

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
District of Tofino
Construction start
Sep 26, 2022(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction end9 months earlyforecast Dec 19, 2025