District of Tofino Wastewater Treatment Plant
Federal contribution
$875,000
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- District of Tofino
- Construction start
- Oct 21, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start12 months earlyforecast Oct 15, 2018
- Construction end16 months earlyforecast Aug 3, 2020
Also in Tofino
- Secondary Wastewater Treatment and System Upgrades$22.0M
- Tofino - Secondary Wastewater Treatment and System Upgrades Phase 2$9.0M
- Clayoquot Sound Biosphere Centre$7.2M
- Pacific IPCA Innovation Centre Deep-Energy Retrofit, Net-Zero Energy Strategy, and Accessibility Upgrade$4.7M
- Barrs Mountain Reservoir Upgrade$383.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49851 in the federal list. How to read these figures.