Back to projects

Pacific IPCA Innovation Centre Deep-Energy Retrofit, Net-Zero Energy Strategy, and Accessibility Upgrade

Tofino, British Columbia

completeOtherGICB
Federal contribution
$4.7M
$4,676,969
Federal share95%

of $4.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 8, 2023
2023202420252026
Built

Approved 18 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
IISAAK OLAM Foundation
Construction start
Apr 1, 2023(actual)
Construction end
Nov 30, 2025(actual)

Against the original forecast

  • Construction start11 months earlyforecast Mar 1, 2024
  • Construction end5 months lateforecast Jul 15, 2025

Also in Tofino