Realignment of Fifth Concession Road in Plummer Additional
Federal contribution
$735,000
Federal share60%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2019
2020202220242026
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Plummer Additional
- Construction start
- Mar 15, 2023(actual)
- Construction end
- Nov 30, 2025(actual)