Rehabilitation - Plummer Additional Township Office/Garage

Plummer Additional, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
20222023
Built

Approved 7 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 10, 2023(actual)
Construction end
Aug 1, 2023(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Jun 1, 2023
  • Construction end5 months earlyforecast Dec 31, 2023

Also in Plummer Additional