Plummer Road Drainage and Erosion Improvements; install 750mm x 18m stormwater culvert along 300 metres of Plummer Road
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Plummer Additional
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Feb 28, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Mar 1, 2017
- Construction end4 weeks earlyforecast Mar 31, 2018
Also in Plummer Additional
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50192 in the federal list. How to read these figures.