Tuktoyaktuk Community Road Upgrades
Tuktoyaktuk, Northwest Territories
Federal contribution
$1.5M
$1,500,750
Federal share75%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2019
today
2020202220242026
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Hamlet of Tuktoyaktuk
- Construction start
- Jul 1, 2021(actual)
- Construction end
- Nov 30, 2026(forecast)
Also in Tuktoyaktuk
- Coastal protection structures to mitigate shoreline erosion in Tuktoyaktuk$53.7M
- Inuvik to Tuktoyaktuk Fibre Link$14.8M
- Tuktoyaktuk Water Treatment Plant Upgrade - Design Completion and Construction$2.9M
- Tuktoyaktuk Community Road Upgrades Phase 2$2.3M
- Tuktoyaktuk Air Terminal Building Replacement$700.0K