Back to projects

Tuktoyaktuk Community Road Upgrades Phase 2

Tuktoyaktuk, Northwest Territories

underwayHighways and RoadsRNIS
Federal contribution
$2.3M
$2,250,000
Federal share75%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2021
today
202220232024202520262027
BuiltForecast

Approved 5 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Hamlet of Tuktoyaktuk
Construction start
Jun 1, 2022(actual)
Construction end
Oct 31, 2026(forecast)

Also in Tuktoyaktuk

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60220 in the federal list. How to read these figures.