Coastal protection structures to mitigate shoreline erosion in Tuktoyaktuk

Tuktoyaktuk, Northwest Territories

completeDisaster MitigationDMAF
Federal contribution
$53.7M
$53,717,032
Federal share100%

of $53.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 27, 2023
20242025
Built

Approved 5 months before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Construction start
Feb 26, 2024(actual)
Construction end
Aug 29, 2025(actual)

Against the original forecast

  • Construction start19 months lateforecast Aug 1, 2022
  • Construction end15 months earlyforecast Dec 1, 2026

Also in Tuktoyaktuk

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62448 in the federal list. How to read these figures.