Coastal protection structures to mitigate shoreline erosion in Tuktoyaktuk
Tuktoyaktuk, Northwest Territories
Federal contribution
$53.7M
$53,717,032
Federal share100%
of $53.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2023
20242025
Built
Approved 5 months before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Hamlet of Tuktoyaktuk and Inuvialuit Regional Corporation
- Construction start
- Feb 26, 2024(actual)
- Construction end
- Aug 29, 2025(actual)
Against the original forecast
- Construction start19 months lateforecast Aug 1, 2022
- Construction end15 months earlyforecast Dec 1, 2026
Also in Tuktoyaktuk
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62448 in the federal list. How to read these figures.