Hay River Solid Waste Management Improvement

Hay River, Northwest Territories

underwaySolid Waste ManagementGIS
Federal contribution
$412,500
Federal share69%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2019
today
20202022202420262028
BuiltForecast

Approved 2 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Hay River
Construction start
Aug 2, 2022(actual)
Construction end
Oct 31, 2027(forecast)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2022