Etwell Bridge Replacement
Federal contribution
$284,588
Federal share50%
of $569.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2019
2020
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Corporation of the Town of Huntsville
- Construction start
- Apr 1, 2020(actual)
- Construction end
- Aug 5, 2020(actual)
Against the original forecast
- Construction end8 weeks earlyforecast Sep 30, 2020