Upgrade of the Roadway Across Beaver Dam Creek on Sitch Road

O'Connor, Ontario

completeHighways and RoadsRNIS
Federal contribution
$68,425
Federal share60%

of $114.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 14, 2019
2020
Built
Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Township of O'Connor
Construction start
Aug 10, 2020(actual)
Construction end
Sep 30, 2020(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 15, 2020
  • Construction end4 weeks lateforecast Sep 1, 2020

Also in O'Connor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54200 in the federal list. How to read these figures.