Back to projects

Replacement of Approximately 62 Stormwater Culverts Township Wide

O'Connor, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share33%

of $151.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of O'Connor
Construction start
Jul 10, 2017(actual)
Construction end
Oct 19, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017
  • Construction end2 months earlyforecast Dec 31, 2017

Also in O'Connor