Replacement of Approximately 62 Stormwater Culverts Township Wide
Federal contribution
$50,000
Federal share33%
of $151.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of O'Connor
- Construction start
- Jul 10, 2017(actual)
- Construction end
- Oct 19, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end2 months earlyforecast Dec 31, 2017
Also in O'Connor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49195 in the federal list. How to read these figures.