Retrofit of O'Connor Municipal Garage
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of O'Connor
- Construction start
- Oct 5, 2022(actual)
- Construction end
- Feb 29, 2024(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 12, 2022
- Construction end4 months earlyforecast Jun 30, 2024
Also in O'Connor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59715 in the federal list. How to read these figures.