Retrofit of O'Connor Municipal Garage

O'Connor, Ontario

completeVentilationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
202220232024
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of O'Connor
Construction start
Oct 5, 2022(actual)
Construction end
Feb 29, 2024(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 12, 2022
  • Construction end4 months earlyforecast Jun 30, 2024

Also in O'Connor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59715 in the federal list. How to read these figures.