Back to projects

Town of Amherst - LaPlanche River Lift Station Upgrades

Amherst, Nova Scotia

completeWastewaterGIS
Federal contribution
$47,945
Federal share40%

of $119.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2019
2020
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Amherst
Construction start
May 26, 2020(actual)
Construction end
Aug 18, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Dec 15, 2019
  • Construction end2 months lateforecast Jun 5, 2020

Also in Amherst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54236 in the federal list. How to read these figures.