Rehabilitation of 10th Sideroad and Concession 6 Road
Federal contribution
$1.8M
$1,768,923
Federal share60%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
20202021202220232024
Built
Approved 5 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Tehkummah
- Construction start
- May 1, 2020(actual)
- Construction end
- Nov 30, 2023(actual)
Also in Tehkummah
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54294 in the federal list. How to read these figures.