Supervisory Control and Data Acquisition (SCADA) System Purchase and Installation
Federal contribution
$50,608
Federal share50%
of $101.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Tehkummah
- Construction start
- May 1, 2017(actual)
- Construction end
- Dec 15, 2017(actual)
Against the original forecast
- Construction end2 months lateforecast Sep 30, 2017
Also in Tehkummah
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48349 in the federal list. How to read these figures.