Indoor Air Quality and Accessibility Upgrades
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Tehkummah
- Construction start
- Oct 1, 2021(actual)
- Construction end
- Dec 30, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast May 3, 2021
- Construction end3 months lateforecast Sep 30, 2022
Also in Tehkummah
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58954 in the federal list. How to read these figures.