Rehabilitation of the Beechwood Bridge

North Middlesex, Ontario

completeHighways and RoadsRNIS
Federal contribution
$1.1M
$1,150,000
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2019
20202021
Built
Program
Rural & Northern Infrastructure Stream
Construction start
Sep 21, 2020(actual)
Construction end
Jun 30, 2021(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Jul 31, 2021