Public Works Building Repairs and Upgrades

North Middlesex, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 18, 2022(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction end2 months lateforecast Nov 1, 2022