Rehabilitation of Parkhill Main Street Watermain and North Middlesex Water Systems
Federal contribution
$3.6M
$3,617,900
Federal share40%
of $9.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
2023
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of North Middlesex
- Construction start
- Sep 26, 2022(actual)
- Construction end
- Sep 26, 2023(actual)
Also in North Middlesex