Second Line Bridge Replacement

Southwold, Ontario

completeHighways and RoadsRNIS
Federal contribution
$299,103
Federal share60%

of $498.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Township of Southwold
Construction start
Dec 1, 2021(actual)
Construction end
Aug 30, 2022(actual)

Against the original forecast

  • Construction start5 months lateforecast Jul 1, 2021
  • Construction end3 months lateforecast May 31, 2022