Construction of Multi-Use Trails in Township Parks
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Southwold
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Jul 8, 2022(actual)
Against the original forecast
- Construction end3 months earlyforecast Sep 30, 2022
Also in Southwold
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59772 in the federal list. How to read these figures.