Installation of New 300 mm Sanitary Sewer Trunk Line (Phase 1) on Talbotville Gore Road
Federal contribution
$257,989
Federal share37%
of $693.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Southwold
- Construction start
- Sep 15, 2017(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction end7 months lateforecast Nov 24, 2017
Also in Southwold
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48683 in the federal list. How to read these figures.