Reconstruction of Plank Road
Federal contribution
$2.5M
$2,500,000
Federal share50%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 22, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Corporation of the City of Sarnia.
- Construction start
- May 18, 2022(actual)
- Construction end
- Nov 28, 2024(actual)