Maple Hill Road Reconstruction
Federal contribution
$811,475
Federal share60%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of Powassan
- Construction start
- Aug 23, 2021(actual)
- Construction end
- Dec 24, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2021