HVAC and air quality improvement
Federal contribution
$4.3M
$4,258,358
Federal share80%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
202220232024
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Board of Management for the District of Parry Sound East - Eastholme Home for the Aged
- Construction start
- May 1, 2021(actual)
- Construction end
- Mar 31, 2024(actual)
Against the original forecast
- Construction start13 months earlyforecast Jun 6, 2022
- Construction end3 months lateforecast Dec 31, 2023
Also in Powassan