Back to projects

HVAC and air quality improvement

Powassan, Ontario

completeVentilationCVRIS
Federal contribution
$4.3M
$4,258,358
Federal share80%

of $5.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 1, 2021(actual)
Construction end
Mar 31, 2024(actual)

Against the original forecast

  • Construction start13 months earlyforecast Jun 6, 2022
  • Construction end3 months lateforecast Dec 31, 2023

Also in Powassan