Addressing Accessibility Deficiencies at the Trout Creek Community Centre

Powassan, Ontario

completeRecreationCCRIS
Federal contribution
$75,378
Federal share40%

of $188.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 23, 2021
20212022202320242025
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Municipality of Powassan
Construction start
Sep 1, 2025(actual)
Construction end
Sep 30, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2025
  • Construction end4 weeks earlyforecast Oct 31, 2025