McEwing Bridge Replacement

Saugeen Shores, Ontario

completeHighways and RoadsRNIS
Federal contribution
$1.1M
$1,085,950
Federal share50%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2020
2021
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Saugeen Shores
Construction start
May 3, 2021(actual)
Construction end
Nov 1, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 4, 2021
  • Construction end13 months earlyforecast Nov 25, 2022

Also in Saugeen Shores

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54629 in the federal list. How to read these figures.