Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Saugeen Shores
Construction start
Oct 3, 2022(actual)
Construction end
Feb 2, 2023(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 5, 2022
  • Construction end7 weeks lateforecast Dec 16, 2022