Installation of New Watermain on Concession 6 to Facilitate Expansion for growth demand

Saugeen Shores, Ontario

completeDrinking WaterCWWF
Federal contribution
$220,969
Federal share50%

of $441.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 16, 2017
ApprovedMar 27, 2018
20182019
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Saugeen Shores
Construction start
Oct 23, 2017(actual)
Construction end
May 17, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 1, 2017
  • Construction end9 months lateforecast Aug 1, 2018

Also in Saugeen Shores

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48447 in the federal list. How to read these figures.