Replacement of Six (6) Conventional Transit Buses

Niagara Falls, Ontario

completePublic TransitPTIS
Federal contribution
$1.9M
$1,870,000
Federal share40%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2020
20202021
Built

Approved 5 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Jan 7, 2020(actual)
Construction end
Oct 25, 2021(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2021

Also in Niagara Falls

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54653 in the federal list. How to read these figures.