Refurbishment of Four Conventional Transit Buses

Niagara Falls, Ontario

completePublic TransitPTIS
Federal contribution
$227,872
Federal share50%

of $455.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2020
2021
Built

Approved 5 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Aug 12, 2020(actual)
Construction end
Sep 30, 2021(actual)

Against the original forecast

  • Construction start11 months lateforecast Sep 3, 2019
  • Construction end3 months earlyforecast Dec 31, 2021

Also in Niagara Falls

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54710 in the federal list. How to read these figures.